A Group Technology (GT) production facility uses 7 machines (a - g) to process 8 parts (1 - 8) as shown in the table below. Order the part-machine matrix using the binary ordering algorithm. Comment...


A Group Technology (GT) production facility uses 7 machines (a - g) to process 8 parts<br>(1 - 8) as shown in the table below. Order the part-machine matrix using the binary<br>ordering algorithm. Comment on the result.<br>1<br>2 3 4 5 6<br>7<br>8<br>a<br>1<br>1<br>b<br>1<br>1<br>1<br>с<br>1<br>1<br>1<br>d<br>1<br>1<br>1<br>1<br>e<br>1<br>1<br>1<br>1<br>f<br>1<br>1<br>g<br>1<br>1<br>

Extracted text: A Group Technology (GT) production facility uses 7 machines (a - g) to process 8 parts (1 - 8) as shown in the table below. Order the part-machine matrix using the binary ordering algorithm. Comment on the result. 1 2 3 4 5 6 7 8 a 1 1 b 1 1 1 с 1 1 1 d 1 1 1 1 e 1 1 1 1 f 1 1 g 1 1