A generating station has the following daily load cycle: Time (Hours)0-55-8 8 – 12 12 – 15 15 – 20 20 – 24 Load (MW) 20 40 60 50 80 40 Draw the load curve and find (i) maximum demand (ii) units...


A generating station has the following daily load cycle:<br>Time (Hours)0-55-8 8 – 12 12 – 15 15 – 20 20 – 24<br>Load (MW)<br>20<br>40<br>60<br>50<br>80<br>40<br>Draw the load curve and find (i) maximum demand (ii) units generated per day<br>(iii) average load and (iv) load factor.<br>

Extracted text: A generating station has the following daily load cycle: Time (Hours)0-55-8 8 – 12 12 – 15 15 – 20 20 – 24 Load (MW) 20 40 60 50 80 40 Draw the load curve and find (i) maximum demand (ii) units generated per day (iii) average load and (iv) load factor.