A contractor has 5o men of the same capacity at work on a job. They can complete the job in 30 days, the working day being 8 hours, but the contract expires in 20 days. He decides to or put 20...

1A contractor has 5o men of the same capacity at work on a job. They can complete the job in<br>30 days, the working day being 8 hours, but the contract expires in 20 days. He decides to or<br>put 20 additional men. If all men get Php 3.00 per day for a full part day and if the liquidated<br>damages are Php 100 for every full or part day he requires over his contract time, in how<br>many days could he finish the job and how much would be his savings if he pays liquidated<br>damages for the delay of the project.<br>

Extracted text: A contractor has 5o men of the same capacity at work on a job. They can complete the job in 30 days, the working day being 8 hours, but the contract expires in 20 days. He decides to or put 20 additional men. If all men get Php 3.00 per day for a full part day and if the liquidated damages are Php 100 for every full or part day he requires over his contract time, in how many days could he finish the job and how much would be his savings if he pays liquidated damages for the delay of the project.

Jun 09, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here