a) Consider 4 processes P0, P1, P2 and P3 that need to share 3 resource types A (10 instances), B (6 instances) and C (7 instances). The allocation of resources and the maximum need for 4 processes as...



a)
Consider 4 processes P0, P1, P2 and P3 that need to share 3 resource types A (10 instances), B (6 instances) and C (7 instances). The allocation of resources and the maximum need for 4 processes as mentioned in the table.


Process             Allocation             Max
                         A B C                    A B C
P0                    0 1 0                      7 5 3
P1                    2 0 0                      3 2 2
P2                    3 0 2                      9 0 2
P3                    2 1 1                      2 2 2


Does the sequence of processes < p1,="" p3,="" p2,="" p0=""> satisfy the safety criteria?
Note: Provide the working for each step.