A company has a project that consists of 11 activities, described in the file P15_25.xlsx. Draw an AON project network and then find the critical path and the minimum number of days required to...


A company has a project that consists of 11 activities, described in the file P15_25.xlsx. Draw an AON project network and then find the critical path and the minimum number of days required to complete this project. Also, create the associated Gantt chart.