A company currently in the 3rd month of a 2 year project. The financial committee would like to have a cost status report. At this stage of the project there is an estimated planned value of 37500....


A company currently in the 3rd month of a 2 year project. The financial committee would like to have<br>a cost status report. At this stage of the project there is an estimated planned value of 37500. The<br>rate of performance is determined at 95% and the current costs have accumulated to 400000.<br>Determine the Budget at completion)<br>

Extracted text: A company currently in the 3rd month of a 2 year project. The financial committee would like to have a cost status report. At this stage of the project there is an estimated planned value of 37500. The rate of performance is determined at 95% and the current costs have accumulated to 400000. Determine the Budget at completion)

Jun 02, 2022
SOLUTION.PDF