9Estimates for a construction project appear in the following table: Dear optimistic most likely pessimistic Cost ($) 60,000 80,000 120,000 Annual profit ($) 16,000 15,000 13,500 Useful life (years...

9 Estimates for a construction project appear in the following table: Dear optimistic most likely pessimistic Cost ($) 60,000 80,000 120,000 Annual profit ($) 16,000 15,000 13,500 Useful life (years) 10 10 10 Residual value ($) 0 0 0 a)Calculate the weighted average for costs and benefits, assigning 4 times more weight to the most probable estimate. b. Calculate the average internal rate of return. c)Weighted Average of Cost d)Weighted Average of Annual Profits e)Average internal rate of return

Jun 02, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here