9. An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is A) 5.00. B) 5.33. C) 5.67. D) 17.00. E) 0.533.





9.


An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5,
and pessimistic = 10. Its expected time is


A) 5.00.
B) 5.33.
C) 5.67.
D) 17.00.
E) 0.533.


Dec 05, 2021
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here