51. The traditional approach in project management is also referred to as the _________________ approach. Agile Extreme Scrum Waterfall 52. The project schedule is primarily used to determine all of...




51.
The traditional approach in project management is also referred to as the _________________ approach.
Agile



Extreme



Scrum



Waterfall




52.



The project schedule is primarily used to determine all of the following except _______________ .



cost estimates



activity start times



activity end dates



slack times



activity end dates




53.



Project managers have the highest level of authority and the most power in the _________ organizational structure



projectized



matrix



functional



traditional




54.



Which of the following best describes the activities that occur during the "Executing" phase of a project?



Project plans are put into action.



Project performance measures are compared with expected performance



Project plans are developed



Projects receive approval from the executive branch of the organization.




55.



The beta distribution (also called the three point method) is useful when estimating activity completion times because it requires three estimates rather than one. It is particularly useful because it forces the person making these estimates to think about the worst-case, most likely and best-case scenarios.



True



False




56.



You are involved in estimating the time it will take to implement a new software package. You have learned that the most likely time will be 60 days. The pessimistic or longest it should take would be 72 days. If everything goes well the shortest possible time is 48 days. What is the weighed average or expected time using the beta (also called three-point method) distribution?



30



54



60



66




57.



A planning process that identifies the threats to a project and has as its objective the reduction in the probability of these threats is called _________________ .



Scope Control



Schedule Decomposition



Control Enhancement



Risk Mitigation




58.



If an activity takes 21 weeks and the earliest it can start is week 41, when is the latest it can start if it is on the critical path.



Week 41



Week 52



Week 62



Not enough information given.




59.



The Project Management Institute (PMI) defines the __________________ as a collection of proven practices that are widely applied by professionals to practice the profession of Project management



Project Management Skill Set (PMSS)



Project Methodology Framework (PMF)



Project Management Body of Knowledge (PMBOK)



Work Breakdown Process (WBP)




60.



Product and project life-cycles are almost always the same.



True



False


Dec 09, 2021
SOLUTION.PDF

Get Answer To This Question