5. Which of the following is provided by a project network but not by the work breakdown structure? A. Dependencies B. Sequencing C. Timing D. Both A and B are correct E. A, B, and C are all correct





5.


Which of the following is provided by a project network but not by the work breakdown structure?
A.
Dependencies
B.
Sequencing


C.
Timing
D.
Both A and B are correct
E.
A, B, and C are all correct