48.Cycle time includes:
A. Processing time, storage and waiting time, movement time, and inspection time.
B. Processing time, inspection time, and inventory time.
C. Processing time, storage and waiting time, finishing time, and selling time.
D. Processing time, storage and waiting time, movement time, and finishing time.
49.During cycle time, value is added only during:
A. Processing time.
B. Storage and waiting time.
C. Movement time.
D. Inspection time.
50.Which of the following elements in a product's cycle time should be maximized?
A. Storage and waiting time.
B. Processing time.
C. Movement time.
D. Inspection time.
51.Four categories of costs associated with product quality are:
A. External failure, internal failure, prevention, and carrying.
B. External failure, internal failure, prevention, and appraisal.
C. External failure, internal failure, training, and appraisal.
D. Warranty, product liability, prevention, and training.
52.Which of the following is
not
an example of the cost of quality?
A. Prevention costs.
B. Internal failure costs.
C. Target costs.
D. Appraisal costs.
53.Which of the following is
not
a prevention cost?
A. Training costs.
B. Warranty costs.
C. Maintenance costs.
D. Quality planning costs.
54.Quality costs do
not
include:
A. Costs to prevent poor quality from occurring.
B. Costs of appraising and inspecting the product.
C. Costs to correct problems before the customer receives the goods.
D. Advertising costs.
55.External failure costs include:
A. Inspections of materials.
B. Training.
C. Rework.
D. Repairs.
56.Refer to the information above. What are the total prevention costs for the Abrams Corporation?
A. $38,300.
B. $34,500.
C. $19,700.
D. $35,250.
57.Refer to the information above. What are the total appraisal costs for the Abrams Corporation?
A. $38,300.
B. $34,500.
C. $19,700.
D. $35,250.
58.Refer to the information above. What are the total internal failure costs for the Abrams Corporation?
A. $38,300.
B. $34,500.
C. $19,700.
D. $35,250.
59.Refer to the information above. What are the total external failure costs for the Abrams Corporation?
A. $38,300.
B. $34,500.
C. $19,700.
D. $35,250.
60.Refer to the information above. As a percentage of total costs, which quality cost category is the highest?
A. Prevention.
B. Internal failure.
C. Appraisal.
D. External failure.