46. _____ address where the project stands in terms of meeting scope, time, and cost goals. a. Technical reports c. Progress reports b. Status reports d. Lessons-learned reports





46.


_____ address where the project stands in terms of meeting scope, time, and cost goals.
a.
Technical reports
c.
Progress reports


b.
Status reports
d.
Lessons-learned reports