ABC, Inc. works on a P5,250,000 contract in 2022 to construct an office building. During 2022, ABC, Inc. uses the cost to cost method. At December 31, 2022, the balances in certain accounts were: Construction in progress – P1,890,000; accounts receivable – P180,000; and billings on construction in process – P900,000; contract retention – P90,000; mobilization fee – P70,000. At December 31,2022, the estimated costs to completion are P2,352,000.
How much is the realized gross profit in 2022?