Please help solve this homework problem. I don’t understand show all work so i can understand please thank you!
Extracted text: 4. The following are given for a natural soil deposit: Moist unit weight, = 17.8 kN/m3 Moisture content, = 15 % Gs= 2.7 This soil is to be excavated and transported to a construction site for use in a compacted fill. If the specification calls for the soil to be compacted at least to a dry unit weight of 18.4 kN/m³at the same moisture content of 15%, how many cubic meters of soil from the excavation site are needed to produce 16000 m3 of compacted fill? Total volume of soil to be excavated = bie