38. Which of the following is a similarity between scope control and schedule control? a. Both are initial processes of project time management. c. Both are portions of the integrated change control...





38.


Which of the following is a similarity between scope control and schedule control?
a.
Both are initial processes of project time


management.
c.
Both are portions of the integrated change

control process under project integration

management.
b.
Both of their primary goals is to define

project goals and milestones.
d.
Both of these processes should occur

before estimating activity durations.