34) Procedures that monitor emerging project scope against the original baseline scope are called: A) configuration control. B) design control. C) trend monitoring. D) document control.






34) Procedures that monitor emerging project scope against the original baseline scope are
called:
A)

configuration control.


B) design control.
C) trend monitoring.
D) document control.