A similarity between the crashing technique and the fast tracking technique is that:

a.

both spread out tasks

over a long period of


time to ensure the

quality of work is

maintained.

c.

both can shorten the

time needed to finish

a project.

b.

both invariably result

in increases in total

project costs.

d.

both are network

diagramming

techniques used

primarily to predict

total project duration.