33. In a project network the critical path is the sequence of activities which has the: A) most activities B) most nodes C) most events D) longest time E) greatest variance





33.


In a project network the critical path is the sequence of activities which has the:
A) most activities
B) most nodes
C) most events


D) longest time
E) greatest variance