3. In the method of „Time Daemon" (Berkeley) of clock synchronization, there are 4 computers: the daemon and clients A,B,C. The daemon supplies time 2:00 to all of them. The clocks of clients A,B,C...


3. In the method of „Time Daemon

Extracted text: 3. In the method of „Time Daemon" (Berkeley) of clock synchronization, there are 4 computers: the daemon and clients A,B,C. The daemon supplies time 2:00 to all of them. The clocks of clients A,B,C show 2:10, 1:50, 2.06 respectively. What time would show all the clocks after synchronization lasting 6 minutes?