28) Which list is in proper time order? a) Pre-development, land acquisition, shell construction, stabilization, permanent financing b) Pre-development, land acquisition, shell construction, permanent...


28) Which list is in proper time order?


a) Pre-development, land acquisition, shell construction, stabilization, permanent financing


b) Pre-development, land acquisition, shell construction, permanent financing, stabilization


c) Acquisition, pre-development, shell construction, stabilization, permanent financing


d) Pre-development, land acquisition, stabilization, shell construction, permanent financing


Please ensure accuracy and explain your choice