21. A WBS is a schedule. True False 22. The work flow in a project network diagram is from right to left. True False 23. Every activity on a project network diagram must have a unique identification...




21.
A WBS is a schedule.
True
False

22.
The work flow in a project network diagram is from right to left.
True
False



23.



Every activity on a project network diagram must have a unique identification code or number.



True



False




24.



If an activity takes 2 weeks to complete nd has a latest finish time of 10 weeks then the Latest it can start is week _________ .



12



8



0



Not enough information given.




25.



If you know that an activity on the critical path has a latest finish time of 12 weeks and the activity takes 5 weeks to complete, then the earliest finish time is ________ weeks



12



7



19



Not enough information given.




26.



Activity H will take 11 weeks to complete. It has 2 predecessors, activities F and G. The earliest that F can be completed is week 15 while the earliest that G can be completed is week 10. When is the earliest activity H can be completed?



25



26



30



None of the above




27.



A critical path within a project network is defined by that path that has the greatest slack times for each of the activities.



True



False




28.



In a project network, slack associated with an activity can be calculated by subtracting the latest the activity can finish from the latest it can be started.



True



False




29.



When a client requires that a project must be outlined in a specific way, this is an example of a project ______________ .



statement



constraint



requirements



necessity




30.



An activity in a project network can begin only after all of its predecessors have been completed.



True



False