1.You are managing a project with an EV of $15,000, PV of $12,000, and AC of $11,000. How would you best describe this project?
A. The project is ahead of schedule and within its budget.
B. The project is behind schedule and within its budget.
C. The project is ahead of schedule and over its budget.
D. The project is behind schedule and over its budget.
2. You are using a Pareto chart to examine the defects that have been found during an inspection of your product. Which process are you performing?
A. Manage Quality
B. Plan Quality Management
C. Control Quality
D. Validate Scope
3. You are initiating a project that has a virtual team. Half of your team members will be located in another country, where they are working for a subcontractor. The subcontractor’s team members speak a different language than your team does. When you need to get information to them, it must first be translated. This is an example of:
A. Encoding
B. Transmission
C. Decoding
D. Acknowledgment