A. Expert
B. Referent
C. Reward
D. Punishment
2. You are being hired to manage a highway construction project for a contractor working for Smith County. The sponsor is a project officer who works for the Smith County municipal government. You have three separate teams working all three shifts, with a separate foreman for each team. Each team has members from two different unions, and each union has its own representative. Who is the best person to approve the project charter?
A. The project manager
B. The Smith County project officer
C. The team foreman
D. The two union representatives