1.On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for...


1.On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which

is estimated to cost P31,200,000. The company recognizes construction

revenue over time. Data on this project for 2022-2024 follow:
Contract

Billings
Costs

incurred
Est’d Costs

to Complete
2022 10,500,000 5,460,000 20,540,000
2023 12,500,000 9,984,000 13,156,000
2024 14,440,000 15,756,000 -
The contract contains a penalty clause that penalizes the company a reduction

of P70,000 from the contract price for every week of delay. In 2024, the

contract was delayed for 8 weeks
What is the gross profit for 2024?
A. 1,164,000 C. 1,724,000
B. 1,466,400 D. 1,824,000




2.MOC Construction Company started work on three job sites during the current

year. Any costs incurred are expected to be recoverable. Data relating to

the three jobs are given below:
Site Contract

Price
Cost

Incurred
Estimated Costs

to Complete
Billings on

Contract
Collections

on Billings
1 5,000,000 3,750,000 - 5,000,000 5,000,000
2 7,000,000 1,000,000 4,000,000 900,000 900,000
3 2,500,000 1,000,000 1,000,000 1,500,000 1,000,000
* If the company records revenue over time, how much must be shown as current

asset in the balance sheet of MOC Construction Company as of December 31?
A. 5,500,000 C. 250,000
B. 500,000 D. 100,000
*If the company records revenue at a point in time, how much must be shown as

current asset in the balance sheet of MOC Construction Company as of December

31?
A. 5,100,000 C. 250,000
B. 500,000 D. 100,000



Jun 08, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here