137. Calculate the direct materials price variance. Answer:AQ x AP (18,800 lb. x $2.54/lb.) $47,752 AQ x SP (18,800 lb. x $2.50/lb.) 47,000 Direct material price...





137. Calculate the direct materials price variance.






























Answer:
AQ x AP (18,800 lb. x $2.54/lb.)






$47,752







AQ x SP (18,800 lb. x $2.50/lb.)




47,000







Direct material price variance




$ 752U




Reference: 21_06
















138. Calculate the direct materials quantity variance.






























Answer:
AQ x SP (18,800 lb. x $2.50/lb.)






$47,000







SQ x SP (18,000 lb. x $2.50/lb.)




45,000







Direct materials quantity variance




$ 2,000U




Reference: 21_06
















139. Job #305 was budgeted to require 3.5 hours of labor at $11 per hour. However, it was completed in 3 hours by a person who worked for $14 per hour.



a. What is the total labor cost variance for Job #305?



b. Calculate the direct labor rate and efficiency variance for this job.