137. Calculate the direct materials price variance.
Answer:AQ x AP (18,800 lb. x $2.54/lb.)
$47,752
AQ x SP (18,800 lb. x $2.50/lb.)
47,000
Direct material price variance
$ 752U
Reference: 21_06
138. Calculate the direct materials quantity variance.
Answer:AQ x SP (18,800 lb. x $2.50/lb.)
$47,000
SQ x SP (18,000 lb. x $2.50/lb.)
45,000
Direct materials quantity variance
$ 2,000U
139. Job #305 was budgeted to require 3.5 hours of labor at $11 per hour. However, it was completed in 3 hours by a person who worked for $14 per hour.
a. What is the total labor cost variance for Job #305?
b. Calculate the direct labor rate and efficiency variance for this job.