11. This is calculated by dividing the budgeted actual time ofcompletion by the schedule performance index. This is the newexpected time schedule the project will be completed in based onthe...


11. This is calculated by dividing the budgeted actual time of completion by the schedule performance index. This is the new expected time schedule the project will be completed in based on the performance to date. If the SPI is greater than one, than the project is now expected to finish sooner than originally scheduled.

















A. Estimated Actual Time to Complete
B. Precedence Diagramming Method
C. Schedule Variance
D. Estimate to Complete