1. You are the project manager for a telecommunications project. You are working on the project scope statement. Which of the following is NOT included in this document?
A. Authorization for the project manager to work on the project
B. Requirements that the deliverables must meet
C. A description of the project objectives
D. The list of deliverables that must be created
2. Which of the following is NOT an input to Control Scope?
A. Work performance data
B. Project management plan
C. Requested changes
D. Organizational process assets
3. Which of these processes is not a part of Scope Management?
A. Scope Identification
B. Collect Requirements
C. Control Scope
D. Validate Scope
4. You are the project manager for a new project, and you want to save time creating the WBS. Which is the BEST way to do this?
A. Make decomposition go faster by cutting down the number of deliverables.
B. Use a WBS from a previous project as a template.
C. Don’t create the WBS dictionary.
D. Ask the sponsor to provide the work packages for each deliverable.