1. Why should the GC diligently review a vendor’s shop drawings? 2. Why are RFIs used on construction projects? 3. Why do some designers resist RFIs? 4. Why do some designers welcome RFIs? 5. When is...


1. Why should the GC diligently review a vendor’s shop drawings?


2. Why are RFIs used on construction projects?


3. Why do some designers resist RFIs?


4. Why do some designers welcome RFIs?


5. When is the RFI log reviewed?


6. Who should prepare an RFI?


7. Are verbal RFI responses sometimes acceptable? If so, how should they be ultimately documented?


8. Do all RFIs result in change orders?



May 19, 2022
SOLUTION.PDF

Get Answer To This Question

Submit New Assignment

Copy and Paste Your Assignment Here