1) What is the crash cost per week for Activity B? A. 150 B. 500 C. 1000 D. 1250 2) If the project is crashed as much as possible, how many weeks is activity F crashed? A. 0 B. 2 C. 4 D. 6 3) You are...



1)     What is the crash cost per week for Activity B?


A.   150


B.    500


C.    1000


D.   1250




2)     If the project is crashed as much as possible, how many weeks is activity F crashed?


A.   0


B.    2


C.    4


D.   6


3)     You are the manager of the construction company and your client is offering you a bonus of $400 per week if you get the project done early. As the manager, you want to crash the project to how many weeks?


A.   8


B.    12


C.    14


D.   23