1. Sequence of Activities of The Project - House Building, and draw the Gantt chart. Number| Activity Predecessor Duration 1 Design house and obtain financing 3 months -- Lay foundation 1 2 months 3...


1. Sequence of Activities of The Project - House Building, and draw the Gantt chart.<br>Number| Activity<br>Predecessor<br>Duration<br>1<br>Design house and obtain financing<br>3 months<br>--<br>Lay foundation<br>1<br>2 months<br>3<br>Order and receive materials<br>1<br>1 month<br>4<br>Build house<br>2,3<br>3 months<br>Select paint<br>2, 3<br>1 month<br>Select carper<br>5<br>2 month<br>7<br>Finish work<br>4, 6<br>3 month<br>

Extracted text: 1. Sequence of Activities of The Project - House Building, and draw the Gantt chart. Number| Activity Predecessor Duration 1 Design house and obtain financing 3 months -- Lay foundation 1 2 months 3 Order and receive materials 1 1 month 4 Build house 2,3 3 months Select paint 2, 3 1 month Select carper 5 2 month 7 Finish work 4, 6 3 month