Extracted text: 1. Sequence of Activities of The Project - House Building, and draw the Gantt chart. Number| Activity Predecessor Duration 1 Design house and obtain financing 3 months -- Lay foundation 1 2 months 3 Order and receive materials 1 1 month 4 Build house 2,3 3 months Select paint 2, 3 1 month Select carper 5 2 month 7 Finish work 4, 6 3 month