1. Project risk management process consists of _____
(a) risk identification, risk monitoring and control
(b) risk assessment and risk mitigation
(c) risk assessment only
(d) None of the above
2. If the schedule performance index is larger than 1, it means___
(a) ahead of schedule
(b) behind schedule
(c) over budget
(d) under budget