1) Learning curve theory states that as the quantity of a product produced _______, the man-hours per unit expended producing the product ______ Doubles; decrease by half Decreases; increases Doubles;...


1) Learning curve theory states that as the quantity of a product produced _______, the man-hours per unit expended producing the product ______



Doubles; decrease by half



Decreases; increases



Doubles; decrease at a fixed rate



Decreases; doubles


2) Variability reduction is one way of controlling manufacturing costs



True



False


3) The ____________ has a direct line of communication with the Procuring Contracting Officer, and the __________ has a direct line of communication with the Program Manager



Program Integrator, Contract Management Office



Program Manager, Administrative Contracting Officer



Administrative Contracting Officer, Program Integrator



Contract Management Office, Administrative Contracting Officer


4) Design changes that are made after the beginning of production tend to be equal in cost to changes made prior to production



True



False


5) When both parties agree to definitize a contract change before the work is begun, the change is made contractually through a __________



Constructive Change



Change Order



None of the answers are correct



Supplemental Agreement


6) The cost of achieving quality can be broken down into which THREE of the following areas (Select three answers):



Appraisal



Failure



Prevention



Containment



Assurance


7) A contractor increasing its prices may be caused by changes in one or more of the five elements of manufacturing



True



False


8) Which of the following can negatively impact the learning curve, production costs, and schedule?



Consistent product design



Management emphasis on productivity improvement



Uninterrupted serial production



Inconsistent product design


9) Which process is recommended for those products with the highest volume and the highest standardization on the product continuum?



Batch



Assembly line



Jumbled flow



Continuous flow


10) Any Government employee can make changes to a contract as long as the Government will benefit from the changes



True



False


11) Which of the following is considered to be a practice of “Lean Manufacturing”?



Low levels of inventory



Highly specialized workforce



Mass production



Centralized management control


12) With respect to product improvements, if a modification will not cause an increase in system performance, does not require extensive independent testing, and the system is currently in production, its development and test should be funded with ___________ and modification kits should be funded with ___________



Procurement; Operations & Maintenance (O&M)



Research, Development, Test and Evaluation (RDT&E); Procurement



Procurement; Procurement



O&M; O&M