1. If a customer order is placed on May 1, the company expects to begin processing it on May 10, and the order is shipped on May 20, the manufacturing cycle time is then how many days long? 2. If...


1. If a customer order is placed on May 1, the company expects to begin processing it on May 10, and the order is shipped on May 20, the manufacturing cycle time is then how many days long?


2. If Toyota Motor Company receives an order on May 1, begins production on May 19, and ships the order on May 20 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio?