1. Have you ever been involved in a project that had a collaborative scheduling approach? Was it successful? Why or why not?
2. A few milestones have been shown on the Rose detailed schedule on the companion website. Prepare a separate milestone schedule for management reporting. Include the milestones shown and add five or so additional milestones that you feel would be important to the Reliable Construction Company, the developer, the architect, and/or the City of Portland.