1 Closure of a project generally entails all of the following activities EXCEPT:
ensuring all work has been accomplished.
ensuring all resources have been reassigned.
ensuring all documentation is complete.
updating the project management plan.
2Which of the following reasons might lead to an early contract termination for convenience?
The buyer faces changing priorities.
The seller faces unexpected difficulties.
The seller needs change.
The buyer and seller negotiate a settlement.