1. Calculate E,D,P for Semi-detached software project using Basic cocomo Model where kloc is 2,ab= 2.4,bb=1.15,cb=2.8,db=0.36. 2. A simple ADA program needs 35 LOC per FP. Calculate FP and estimated...

Please answer 2 questions only answered with out explaining.
1. Calculate E,D,P for Semi-detached software project using Basic<br>cocomo Model where kloc is 2,ab= 2.4,bb=1.15,cb=2.8,db=0.36.<br>2. A simple ADA program needs 35 LOC per FP. Calculate FP and<br>estimated size for System with 7 inputs, 7 outputs, 4 Inquiries, 4 Files,<br>2 interfaces?<br>Level of Complexity<br>Component<br>Simple Average<br>Complex<br>Input Item<br>Output Item<br>Inquiry<br>3<br>4<br>4<br>7<br>3<br>4<br>Master File<br>7<br>10<br>15<br>Interface<br>5<br>7<br>10<br>

Extracted text: 1. Calculate E,D,P for Semi-detached software project using Basic cocomo Model where kloc is 2,ab= 2.4,bb=1.15,cb=2.8,db=0.36. 2. A simple ADA program needs 35 LOC per FP. Calculate FP and estimated size for System with 7 inputs, 7 outputs, 4 Inquiries, 4 Files, 2 interfaces? Level of Complexity Component Simple Average Complex Input Item Output Item Inquiry 3 4 4 7 3 4 Master File 7 10 15 Interface 5 7 10

Jun 09, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here